October 29, 2026
On the afternoon of Tuesday, October 6, cars sat parked on the grass at 4705 South Ocean Boulevard. The lot at the south end of Highland Beach is the site the county has planned as a public beach park since 1987, and it still has no way down to the water. That same day, according to CBS12's report, Palm Beach County commissioners approved $85,000 for work on Cam D. Milani Park.
Most people in town heard over the summer that the park was about to break ground. It hasn't. The October vote hired a builder to price the job. Before construction can start, two approvals are still needed: building permits from the town, which were last listed as pending, and a construction price that has to go back to the County Commission. Neither has a public date, so for now any start date is a forecast.
The county's agenda item for October 6 asked commissioners to approve two things. One was a construction manager at risk contract with Kaufman Lynn Construction, Inc. for the park. The other was Task Order No. 1 with Kaufman Lynn for $85,000 in preconstruction services.
CBS12 reported that the approval covers preconstruction work, including cost estimates and scheduling, and does not authorize construction. The county estimates the project at $8.65 million and must bring back a separate construction price for approval.
Kaufman Lynn will now price the job and lay out a schedule. Commissioners will then vote on that number, and no date has been announced for it to come back.
The October vote looks small next to how long the park has been waiting. The county's agenda summary lays out the history:
The county never used its second extension. After it notified the town in 2024, the project became a sequence of steps: design, permits, a builder, a price. October 6 put the builder in place. Permits and the price are still to come.
In spring 2026 the schedule looked close. Minutes from the April 7, 2026 Town Commission meeting record that the county expected to file permit applications within about a week and was aiming to break ground in late May or early June 2026.
The filing happened. The Coastal Star reported that the county submitted permit applications and a compliance package to the town in mid-April, and that construction could begin once the permits were approved. The package included required approvals from the U.S. Army Corps of Engineers and the South Florida Water Management District, along with archaeologists' reports on parts of the property that Native Americans and Japanese farmers once used. Town Manager Marshall Labadie told the paper:
"There were a lot of documents, several thousand pages. The compliance package is very comprehensive, very detailed and very complete."
Labadie also told The Coastal Star that the review could take longer than usual. The project is complex, and it's unlike anything else in a town that has no other parks or public recreation facilities. The town's FY 2026 strategic priorities tracker later listed the compliance package as submitted by its April 17 deadline, showed permits from the Highland Beach Building Department as pending, and moved the expected construction start to September 2026.
September has now passed as well. Each of these targets was set before the county had a builder under contract and before anyone had priced the job. In April, Parks and Recreation Director Jennifer Cirillo estimated construction would take about 18 months, which pointed to fall 2027 if work had started in June. The 18 months still stands as an estimate. It just starts later, on whatever date construction is cleared to begin.
The October agenda describes the project as including a guardhouse with an access-controlled gate at the parking entrance, an elevated boardwalk, a restroom and lifeguard building, a lifeguard station and landscaping. Earlier county descriptions add detail, and some of it may change during preconstruction:
The Coastal Star noted that every beach in Highland Beach is private and the town has no public beach access. Milani Park would be the first.
Parking has been the main point of dispute from the start, and it's also the figure that has changed most. The original plan called for 100 spaces west of A1A. Recent sources give different numbers for the first phase:
| Source | Date | Phase 1 spaces | Later phase |
|---|---|---|---|
| CBS12 | October 6, 2026 | 46 | 54 more, no set timeline |
| Town FY 2026 tracker | FY 2026 working document | 38 | Not stated |
Either way, the first phase is well under half of the original 100. The price that comes back to commissioners will be for a specific design, and the opening-day space count should be settled by then.
Most of the questions residents raised are about the road. Cars would park on the west side of A1A, and people would walk across the state road to the beach. At a resident forum covered by The Coastal Star in spring 2025, county officials described a road-level crossing with distinctive pavement markings and landing points at each end, plus more signage and landscaping kept low enough to preserve sightlines. Assistant County Administrator Isami Ayala-Collazo said a pedestrian bridge was not under discussion, though the county was open to exploring one with the Florida Department of Transportation.
The same report covered how the lot would run, as the county described it in 2025:
Asked about visitors wandering onto private beaches, Cirillo said the county would follow the settlement's restrictions and post signs. She also pointed out that the beach seaward of the mean high-water line is public along Florida's entire coast.
The town is also preparing for the park. The April 2026 minutes record Labadie discussing safety and emergency response at the park with the police and fire chiefs, because the town has no formal mutual aid agreement with the county.
The next public steps are the town's decision on the county's building permits and a Board of County Commissioners agenda item carrying Kaufman Lynn's construction price for Cam D. Milani Park. Construction can begin once both are in place, and about 18 months of building would follow.
The south end of Highland Beach is about to change, and Milani Park is a large part of that, from the gated lot and the A1A crossing to the boardwalk out to Yamato Rock. If you'd like to talk through what the park might mean for your corner of the barrier island, Kelly Gerber would be glad to hear from you. Let's Connect.
With deep local knowledge and a commitment to excellence, Kelly Gerber provides a refined real estate experience built around your success.